Runs have multiple steps. Each step can be unique and will have its own lead time and schedule. In the summary view for a run (Runs -> Click on a run), you can schedule each step's start and end schedule, along with a lead time.
Scheduling both an individual step, along with the entire run
If the run start time and end time are not set but individual steps in the run have start and end times set, the run will automatically set its start and end times to the earliest start and the latest end.
Viewing production schedule
From the main Runs view, click on the Timeline button on the top. Here, you can see all of the runs scheduled in your factory in a Timeline. Below the chart, you can see unscheduled runs.
Clicking one of the items in the left column will pop out the right side and allow you to schedule the run. The timeline window will reflect your changes automatically.